94-43. Policies Concerning Wastewater Pump Stations and Force Mains.

  1. CCWSD will not take ownership of wastewater pump stations/force mains constructed or proposed by others. Wastewater pump stations/force mains increase operating costs, are subject to failure causing spills which degrade the environment and result in fines, can cause major problems during storm events, require additional staff, limit sewer service to the greater community, and encourage development of marginal property rather that directing growth in areas identified by the Board of Commissioners.
  2. One of goals of the Cane Creek Water and Sewer District (CCWSD) is for the District's sewer system to be expanded by developers constructing gravity sewer line extensions. If it isn't technically possible to serve a proposed project with a gravity sewer line, the developer can consider providing the sewer service via a wastewater pump station and force main. However, before the CCWSD will consider issuing a permit for a developer to construct a wastewater pump station and force main, the developer shall have to meet certain requirements, including but not limited to having a North Carolina licensed civil engineer provide the CCWSD with a letter explaining why it is not technically possible to serve the proposed property with a gravity sewer line.