US 176 Update
DN01075- US 176 (US 25 to Henderson County Line} Update
Current Status: Under Construction
Construction Progress: Approximately 20% complete
Recent focus areas:
- Grading existing cut slope failures
- Cleaning ditches
- Seeding disturbed areas
- Upcoming work: Large rock embankment construction expected to begin in the next few weeks, requiring barrier walls and long-term lane closures, which will affect traffic.
Timeline:
- Overall Completion Goal: March 27, 2026
- Intermediate Completion Time (ICT #1): September12, 2025
Utility Coordination & Right of Way:
- Active coordination with Henderson Maintenance, AT&T, and Duke Energy
- NCDOT Right of Way team has secured Right of Entry with most property owners