US 176 Saluda to Tryon

US 176- Saluda to Tryon (Polk County)

Design Progress: Approximately 30% complete

  • ​​​​​Preliminary roadway design completed
  • Geotechnical field work completed as of May 2, 2025 (except for one new site added recently)
  • Awaiting geotechnical slope stability analysis for final recommendations
  • Field survey at Ozone Drive intersection underway; hydraulic design to follow
  • Drainage improvement at Ozone Drive intersection added to project scope
  • Potential wall overlap with Pearson Falls bridge project under review

Surveys & Environmental:

  • Final surveys delivered to TGS (initial surveys by WSP; remaining by TGS)
  • Archaeology and Architecture - NSR received 2/6/2025
  • Other environmental surveys (plant, bat, aquatic, 401/404 permits, Env. Doc)-pending
  • Trout moratorium waived (1/1-5/15) if needed; maintain roadside parking
  • Area includes State Conservation Easement (Pacolet Conservation)

Estimated Cost:

  • $15M (as of 5/1/2025 - Lonnie Watkins)
  • Key Dates:
    • Raleigh Turn-in: August 5, 2025
    • Division Turn-in: August 19, 2025
    • DPOC LET: October 14, 2025
    • DDRL LET: November 18, 2025