Edney Inn Road
SR 1702- Edney Inn Road
Design Progress: 0% complete
- HNTB assigned to project, will begin FSM after receipt of Final Surveys
- Construction Completion Date: Estimated 6/1/2026
- Construction Estimate: Expected under $10M
Let Dates:
- Division Turn-in: 10/14/2025
- Let Date: 12/9/2025
Environmental & Surveys:
- All environmental items (plant, bat, aquatic, permits, etc.): Not yet started
- Final Survey (WSP): Still pending, expected soon
- Survey limits established after site visit with Patrick Eubanks on 2/21/2025
- Repairs from storm damage had to be completed prior to initiating design/survey
Notes:
- Survey request withheld to avoid duplicative work during emergency repairs
- Acceleration of schedule planned once survey data is received