Davis Mountain Road

SR 1188- Davis Mountain Road (Henderson County)

Design Progress: Approximately 20% complete

  • Final survey to be provided by JMT (responsible for all survey needs)
  • Geotechnical investigations completed; geoenvironmental work requested
  • Sewer line update provided by Robert Wilcox; non-scope sites being removed by Wanda Carver
  •  Project schedule updated weekly by JMT; critical path highlighted in red per request

Surveys & Environmental:

  • All environmental items (plant, bat, aquatic, Env. Doc, 401/404, archaeology, architecture) - pending

Estimated Cost:

  • $13M (as of 5/1/2025- Lonnie Watkins)

Key Dates:

  • Raleigh Turn-in: July 8, 2025
  • Division Turn-in: July 15, 2025
  • DPOC LET: September 9, 2025
  • DORL LET: October 21, 2025