Davis Mountain Road
SR 1188- Davis Mountain Road (Henderson County)
Design Progress: Approximately 20% complete
- Final survey to be provided by JMT (responsible for all survey needs)
- Geotechnical investigations completed; geoenvironmental work requested
- Sewer line update provided by Robert Wilcox; non-scope sites being removed by Wanda Carver
- Project schedule updated weekly by JMT; critical path highlighted in red per request
Surveys & Environmental:
- All environmental items (plant, bat, aquatic, Env. Doc, 401/404, archaeology, architecture) - pending
Estimated Cost:
- $13M (as of 5/1/2025- Lonnie Watkins)
Key Dates:
- Raleigh Turn-in: July 8, 2025
- Division Turn-in: July 15, 2025
- DPOC LET: September 9, 2025
- DORL LET: October 21, 2025