Bearwallow Mountain Road
SR 1587- Bearwallow Mountain Road
Design Progress: Approximately 20% complete
- Construction Completion Target: August 2026
- Kimley-Horn received survey on 3/4/2025
- KH beginning plan layout for each site
- Meeting scheduled with Hydraulics Unit on 5/712025 to discuss culvert sizing for Site 1
- Drill work began in April, expected to wrap up by early May
Environmental & Surveys:
- Plant Survey- Not completed
- Bat Survey- Not completed
- Aquatic Survey- Not completed
- Environmental Document- Not completed
- 401/404 Permits- Not completed
- Archaeology-Not completed
- Architecture - Not completed
- KH plans to begin environmental and geotechnical field work in April 2025
Estimated Cost: Expected under $1OM
Let Dates:
- DPOC Let: September 2, 2025
- DORL Let: October 28, 2025