Bearwallow Mountain Road

SR 1587- Bearwallow Mountain Road

Design Progress: Approximately 20% complete

  • Construction Completion Target: August 2026
  • Kimley-Horn received survey on 3/4/2025
  • KH beginning plan layout for each site
  • Meeting scheduled with Hydraulics Unit on 5/712025 to discuss culvert sizing for Site 1
  • Drill work began in April, expected to wrap up by early May

Environmental & Surveys:

  •  Plant Survey- Not completed
  •  Bat Survey- Not completed
  •  Aquatic Survey- Not completed
  •  Environmental Document- Not completed
  •  401/404 Permits- Not completed
  • Archaeology-Not completed
  • Architecture - Not completed
  • KH plans to begin environmental and geotechnical field work in April 2025

Estimated Cost: Expected under $1OM

Let Dates:

  • DPOC Let: September 2, 2025
  • DORL Let: October 28, 2025