Bald Rock Road
SR 1710- Bald Rock Road
Design Progress: Approximately 20% complete
- Construction Completion Target: July 2026
- Man-day estimate/scope submitted to Wanda ("Beefy") for processing
- KCA issued NTP on 2/17/2025
- Survey submitted to KCA on 2/27/2025; updated survey received 4/18/2025 from L&S
- Geotech field work completed; site inventories underway
- KCA identified new site between Sites 8/9 to be included with Site 9; working with GEU on recommendations
- Design criteria submitted 3/27/2025
- DRPS for Sites 2 and 1O being submitted; VHB reviewing
- Met with GEU and Resident Engineer's Office on 5/2 to review wall types and constructability
Environmental & Surveys:
- NRTR and PJD reviewed 4/15/2025
- Tribal coordination sent 4/15/2025
- (X) Archaeology- NSR received 4/3/2025
- (X) Architecture - NSR received 3/13/2025
- Plant, Bat, Aquatic, Env. Doc, 401/404 Permits - Not completed
- Plant surveys scheduled for May 2025
Estimated Cost: Expected under $1OM
Let Date: September 23, 2025