Pot Shoal Road Update

DN01088-Pot Shoal Road Update

Current Status: Road is closed to through traffic due to unsafe conditions.

Construction Progress: Approximately 20% complete

Recent focus areas:

  • Debris and waste material removal to clear blocked drainage pipes
  • Regrading and seeding of slopes
  • Preparation for large rock embankments and soil nail walls (to begin within weeks)

Timeline:

  • Overall Completion Goal: March 11, 2026
  • Intermediate Completion Time (ICT #1): September 12, 2025

Utility Coordination & Right of Way:

  • NCDOT R/W has secured Right of Entry with most property owners
  • Active coordination with Henderson Maintenance, AT&T, and Duke Energy

Duke Energy Work:

Site 2008 (right side from NC 176 past the power plant):

  • Drilling scheduled to begin May 19 and last approximately 3 week
  • Road to remain closed for 5 weeks total (3 weeks Duke+ 2 weeks SOC)

Site 2009 (left side uphill from site 2008)

  • Drilling to begin mid-June, after completion of site 2008
  • Towers will be outside the ROW; final plans pending geotechnical review

Contractor Activities During Duke's Work:

  • While Duke works on site 2008, SOC will:
  • Seed slopes, inspect and repair pipes, grade ditches
  • Backfill behind headwall with soil/riprap and construct riprap ditch​​​​​​​
  • After Duke completes site 2008, SOC will swap to that location to complete road repairs (~2 weeks)

Anticipated Milestone:

  • By early July, SOC should complete work past the power plant
  • When Duke returns in August/September, no further schedule conflicts expected

Estimated Completion of SOC Scope: Late August to early September, assuming Duke's drilling stays on track