Pearson Falls Road (Polk Co)

SR 1102- Pearson Falls Road (Polk County)

Design Progress: 0% complete

  • LJB assigned to project, will begin FSM after receipt of Final Surveys
  • Construction Completion Date: Estimated 6/1/2026
  • Construction Estimate: Expected under $1OM

Let Dates:

  • Division Turn-in: 10/14/2025
  • Let Date: 12/9/2025

Environmental & Surveys:

All environmental items (plant, bat, aquatic, permits, etc.): Not yet started

  • ​​​​​​​Final Survey (WSP): Still pending, expected soon
  • Survey limits established after site visit with Patrick Eubanks on 2/21/2025
  • Repairs from storm damage had to be completed prior to initiating design/survey

Notes:

  • Roadway·suffered extensive storm damage; large sections were completely washed out
  • Survey request withheld to avoid duplicative work during emergency repairs
  • Extensive geotechnical investigations will be required
  • Acceleration of schedule planned once survey data is received