Pearson Falls Road (Polk Co)
SR 1102- Pearson Falls Road (Polk County)
Design Progress: 0% complete
- LJB assigned to project, will begin FSM after receipt of Final Surveys
- Construction Completion Date: Estimated 6/1/2026
- Construction Estimate: Expected under $1OM
Let Dates:
- Division Turn-in: 10/14/2025
- Let Date: 12/9/2025
Environmental & Surveys:
All environmental items (plant, bat, aquatic, permits, etc.): Not yet started
- Final Survey (WSP): Still pending, expected soon
- Survey limits established after site visit with Patrick Eubanks on 2/21/2025
- Repairs from storm damage had to be completed prior to initiating design/survey
Notes:
- Roadway·suffered extensive storm damage; large sections were completely washed out
- Survey request withheld to avoid duplicative work during emergency repairs
- Extensive geotechnical investigations will be required
- Acceleration of schedule planned once survey data is received