Green River Cove Road
SR 1151 - Green River Cove Road
Design Progress: Approximately 50% complete
- Preliminary roadway design completed along the river section
- Switchback section design pending final geotechnical recommendations (expected this month)
- Geotech borings ~80% complete along the river; ~25% in switchback areas (delayed earlier by wildfires)
- Hydro completed for 50% of the river section; remaining hydro to be completed by end of May
- Final survey delivered to TGS (initial surveys by WSP); TGS completing additional survey
- Sites 423-425 removed (work covered by maintenance contract)
- Outstanding items: permit needs, utility relocations, CE requirements, ROW impacts at major pipe crossings under review
- NRTR being handled by NCDOT
Environmental & Surveys:
- (X) Archaeology- NSR received 12/19/2024
- (X) Architecture - NSR received 12/11/2024
- Plant, Bat, Aquatic, Env. Doc, 401/404 permits- Not completed
- NCWRC comments: No trout moratorium, maintain roadside parking, project adjacent to Game Lands
Estimated Cost:
- $20M (Lonnie Watkins- 5/1/2025)
- Key Dates:
- Raleigh Turn-in: June 3, 2025
- Division Turn-in: June 17, 2025
- DPOC LET: August 12, 2025
- DORL LET: September 16, 2025